This is the endgame schedule for March 2019 Iteration.

Schedule

Note: The Insiders build needs to be in the wild for 24 hours before we can enter the last phase of the endgame.

Monday 03/25
  • Run OSS tool Andre Weinand (@weinand)
    • The LCA review of the ThirdPartyNotices.txt files is not needed anymore
  • Code freeze at 5pm PT
  • Ensure we have a green build on all platforms at 5pm PT
  • All test items contain test meta data by 5pm PT and sufficiently comprehensive test descriptions by 8am CET
  • Update your availability for testing here - https://vscode-tools.azurewebsites.net/
Tuesday 03/26
  • Test plan items assigned (using https://vscode-tools.azurewebsites.net/)
    • Run the tool multiple times to balance load if test items come in later and assignments are already made
  • All closed feature-requests either have a verification-needed or on-testplan tag
  • Test build starts at 7am CET
  • Test plan ready by 8am CET
  • Testing
  • Verification needed
Wednesday 03/27
  • Testing
  • Remind team members to assign issues that they intend to fix to the current milestone
  • Fixing (self-assigned, milestone assigned)
  • Verification
Thursday 03/28
Friday 03/29
Friday/Monday
Monday - Wednesday

Note: The Insiders build needs to be in the wild for 24 hours before we can enter the last phase of the endgame.

Wednesday/Thursday

Activity

  1. dzienisz commented on Apr 4, 2019

    @dzienisz

    What is happening with the last two releases, both were delayed?

  2. weinand commented on Apr 4, 2019

    @weinand
    ContributorAuthor

    Kamil Dzieniszewski (@dzienisz) no, we are always shipping the release in the week after the endgame.
    You can always find the expected release date in the first comment of the endgame (above).

    04/04 Expected release date (this may change)

  3. weinand commented on Apr 4, 2019

    @weinand
    ContributorAuthor

    March released shipped!

  4. dzienisz commented on Apr 5, 2019

    @dzienisz

    Andre Weinand (@weinand) thanks for the answer!

  5. locked and limited conversation to collaborators on May 20, 2019
Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment

Metadata

Metadata

Labels

endgame-planVS Code - Next release plan for endgame

Type

No type

Projects

No projects

    Milestone

    Relationships

    None yet

    Development

    No branches or pull requests

    Issue actions